FRUITPORT, MI – The three-year Fruitport Excessive Faculty development mission is underway and forward of schedule. 

Development on the $48.7 million mission started in March and is six to eight weeks forward of schedule, stated Dave Hazecamp, president of the Fruitport Group Colleges Board of Schooling. 

Two new wings are starting to take form and a few renovated areas are already in use. Development started in March.

The mission will lead to a 75-80 p.c new highschool in the identical location, 357 N. sixth Ave., as the unique 1950s constructing. The plan entails demolishing and developing in phases. Completion is anticipated in August 2021. 

READ  New Netflix star on the highs and lows of Hollywood

“We save about 45 million by re-purposing a part of the constructing,” Hazecamp stated. “It will be a very stunning constructing when it is finished. … It is a good use of taxpayer {dollars} to maintain the a part of the outdated constructing, however the draw back is it takes longer.” 

Parts that will likely be saved and included into the brand new college had been constructed within the 1990s. 

College students and academics are already occupying the primary renovated school rooms which can be for engineering/drafting and artwork, stated Superintendent Bob Szymoniak. A hallway of showcases can be new this fall. 

Occupancy of the brand new weight room and boys’ varsity locker room is anticipated in October. 

READ  Nuggets lengthen Trey Lyles qualifying provide; ahead now a restricted free agent

Here is a timeline of the work forward, in accordance with district web site:  

  • December 2019: Occupancy for the cafeteria, kitchen, two-story classroom space and woodshop 
  • June 2019: Begin science wing transform 
  • August 2019: Occupancy for science wing school rooms 
  • January 2020: Begin demo 4 hallways and a locker room space; begin development on the women’ varsity room and robotics space 
  • February 2020: Begin development on the commons space, workplaces, media heart and music space 
  • August 2020: Occupancy for the women’ crew room and robotics space 
  • April 2020: Occupancy for the auditorium. 
  • February 2021: Begin demo of the remaining locker room space; Begin development on the MOCI kitchen space and PE locker rooms. 
  • April 2021: Occupancy for the commons space, workplaces, media heart and music space 
  • Could 2021: Begin demo of the present auditorium, workplaces, media heart and the rest of 1 hallway 
  • August 2021: Occupancy for the MOCI kitchen and PE locker rooms 
READ  Kyle Freeland primed to rebound, assist get Rockies again on monitor

“It is unbelievably exiting to look at the progress of this mission,” Szymoniak stated. “It is created a optimistic vibe in the neighborhood – persons are actually enthusiastic about it.”

Fruitport celebrates begin of $48.7 million highschool renovation

Funding comes from a voter-approved as much as 30-year, 3.9 mill bond concern from 2016. It’s anticipated to generate about $50.6 million for highschool development and minor enhancements at different buildings.   